Scheduling Test Runs
Lesson 4 · Running Tests
Scheduling Test Runs
You can specify a date and time, and set conditions for executing a test in
the Execution Flow tab. A condition is based on the results of another
specified test in the Execution Flow. By setting conditions, you can instruct
TestDirector to postpone execution of the current test until the other
specified test has either finished running or passed. You can also set the
sequence in which to execute the tests.
For example, suppose you schedule to run Test 2 only after Test 1 has
finished, and run Test 3 only if Test 2 passed. You can also schedule Test 1
and Test 2 to run a day before Test 3. Unlike the Execution Grid, which
displays the tests with only test run information, the Execution Flow
displays the tests with conditions in a diagram.